• Are the houses you're building in KY acres, lots 308, 309 & 314, the same 2 story house as on lots 315, 333 & 321 that are completed?? Do you also plan on putting the same 2 story house on lot 317 as well?

    Read More...
  • Sorry don't post, yes houses on lots 155 and 156 are still available

    Read More...
  • Is the home u r constructing on lot #156 in Summit Park available? What are you asking for it? Thanks!

    Read More...
  • Time for another update, lot 330 cabinets are set and tops are being measured this week. Trim has been delivered and Kevin starts today. Water meter installed and septic system should be installed as soon as weather permits. The electrician starts his rough in at lot 306 today and we should be insulating this week.…

    Read More...
  • The end of a good week. Lot 330 the drywall is hung the electric meter will be set Monday with drywall finishingstarting then. trim to be delivered January 26th with Kevin startting the 27th. Stne and brick have started on lot 306. Rough ins have not started due to cold temps. We're more than half…

    Read More...
  • Latest on Lot 330. We wil finish insulation today and delivering drywal this wen. Brick and vinyl are completed. Water line and electric line are called in for inspection. Garage door ordered. We are finally getting the inside finished.

    Read More...
  • Well, we need to be in the boat building business. Lot 330's exterior is almost complete. On ly lackin front cedar shake siding and some trim. HVAC rough, plumbing rough, and electrical almost complete. Hope to inspect this week and perhaps insulate this week.

    Read More...
  • Update on all 3 homes, Lot 330 is framed and brick is being delivered Monday. The plumber starts Tue with HVAV and Elect after that. Lots 315 & 306 slabs were poured yesterday. I had to scrape the streets in front of 315, very muddy. We will also be back filling 315 and 306 tomorrow.…

    Read More...
  • Read More...
  • Read More...
  • Raining again will postpone plumbing ground works. Should be able to start tomorrow with lot 330. Framing for panels and trusses was ordered yesterday and should be delivered right after foundations ready. Looking forward to starting the serious work! Picking out flooring and scheduled to look at cabinets this week.

    Read More...
  • Raining today will delay the plumbing ground works for lots 306 & 330. The wall panels for lot 315 should be set by Friday. Hopefully the rain will not last long this week and we can proceed with pouring the slabs so framing can start

    Read More...
  • Read More...
  • Read More...
  • Read More...
  • Read More...